Programme Owner: Sebastin
Key Stakeholder:Mani
Solution Design: Hari
Project Manager: Ranjith
Developers: Pravitha,Natarajan,Senthil
Testers: TBD
Approver: Sebastin
Poorvika Ecomm Web & App
Project Description
As part of strategic target architecture, To create the dynamic template form and integrate the template via api.
| Capabilities | Dev Start Date | Dev End Date | Dev % Comp | Test % Comp | Go Live Target Date | RAG | Remarks | |
|---|---|---|---|---|---|---|---|---|
| Capability 1 | "Login Page UI Design in Frontend , Redux Integration and Private Route Setup, implementation of JWT Authentication and integration of Login component in Frontend " | 30-06-2022 | 09-07-2022 | 100% | 0% | 30-11-2022 | ||
| Capability 2 | Implementation of User Roles management screen, Implementation of Main Layout in the frontend | 10-07-2022 | 17-07-2022 | 100% | 0% | 30-11-2022 | ||
| Capability 3 | "Frontend UI refactoring with MUI custom theme, Implementation of User crud operation in frontend" | 20-07-2022 | 26-07-2022 | 100% | 0% | 30-11-2022 | ||
| Capability 4 | Implementation of JWT refresh token | 27-07-2022 | 06-08-2022 | 100% | 0% | 30-11-2022 | ||
| Capability 5 | "Setup of development server and deployment of app using CI/CD pipeline Implementation of Role based filter for users and roles page and Sidebar Implementation of Landing container for the template page Layout creation for Template creation page" | 17-08-2022 | 31-08-2022 | 100% | 0% | 30-11-2022 | ||
| Capability 6 | Implementation of drag and drop for grid layout | 01-09-2022 | 11-09-2022 | 100% | 0% | 30-11-2022 | ||
| Capability 7 | "Implementation of multiple components for the template,Implementation of copy content and preview of components in template Implementation of Save dialog and unique name for field value" | 16-09-2022 | 27-09-2022 | 100% | 0% | 30-11-2022 | ||
| Capability 8 | "Implementation of Image and Image Upload field in dynamic template, Implementation of Image upload service to upload file to GCP Display the form via API to the other websites" | 09-10-2022 | 24-10-2022 | 50% | 0% | 30-11-2022 | ||